June 12, 2026 

Division I construction of 13 Mile Road box culvert installation is complete. Jackson Dirt Works is transitioning to open channel work and storm sewer installation along Arthur Road starting June 15, 2026. 13 Mile Road is back open to all traffic.  

Arthur Road Closure Notice Starting June 15, 2025

Arthur Road Closure Map

Division II construction of Northland Drive box culvert installation is complete. Northland Drive is open to all traffic. Deans Excavating is repositioning for storm sewer installation along Gilbert Road starting June 15, 2025. 

May 18, 2026

13 Mile Road Closure Notice Starting May 21, 2026

13 Mile Road Closure Map

April 27, 2026

Northland Drive Closure Notice and Project Update

Northland Drive Closure Detour Map

April 14, 2026

Work starting on April 15, 2026

Division I - Construction Update Map

March 24, 2026

DRAIN CONSTRUCTION NOTICE TONKIN DRAIN

September 24, 2025

Mecosta County Drain Commissioner, Karla Miller announces start of open channel work.

Division I construction has started from the downstream extent of the drain upstream to Northland Drive. Jackson Dirt Works has initiated selective clearing work along the Tonkin Drain. Clearing work is anticipated to continue through Fall 2025.

Construction work zones can be reviewed on the map linked below:

September 24, 2025 Construction Zone Map

For Further Information, Please Contact:
Mecosta County Drain Commissioner
Karla Miller
(231)592-0103
drain@mecostacounty.org

Northland Drive Culvert Installation

13 Mile Road Culvert Installation